| CHANGE LOG - ARTC DIN
Corridor (Victoria) |
|
|
Changes since 1 July
2009 -
Most recent on top |
|
|
|
|
| Change date |
Drawing |
Location |
Details |
|
|
|
|
| 21 Jan 2012 |
V140 |
Geelong C |
S and V indicators swapped positions |
| 22 Dec 2011 |
V138 |
Barwon Park |
Proposed loop |
| 22 Dec 2011 |
V140 |
Geelong - Gheringhap |
New line/loops commissioned |
| 22 Dec 2011 |
V139 |
Geelong - Gheringhap |
New line/loops commissioned |
| 12 Dec 2011 |
V216 |
Wodonga |
Banner repeaters for sigs WOD 4 & 16 installed |
| 12 Dec 2011 |
V214 |
Wangaratta |
Banner repeaters for sigs WRT 6 & 26 installed |
| 12 Dec 2011 |
V211 |
Seymour |
Banner repeater for sig SEY104 installed |
| 16 Nov 2011 |
V127 |
Doeen |
Moved to this sheet |
| 16 Nov 2011 |
V128 |
Wimmera Freight Terminal |
Under construction |
| 28 Sep 2011 |
V139 |
Gheringhap |
NBs at Sig 83/6 |
| 25 Sep 2011 |
V148 |
Dynon |
Sigs DYN 90, 92, 94, 96, 98 now LED |
| 18 Sep 2011 |
V139 |
Gheringhap |
Changes to Gauge splitting |
| 4 Aug 2011 |
V208 |
Passing Lane 2 |
Added E & W line signs - altered clearance length |
| 4 Aug 2011 |
V142 |
Manor Loop |
Dn Dep signal nos corrected |
| 29 Jul 2011 |
V139 |
Moorabool |
New T/O installed at 77.3 |
| 29 Jul 2011 |
V207 |
Passing Loop 2 |
New loop commissioned |
| 29 Jul 2011 |
V208 |
Passing Loop 2 |
New loop commissioned |
| 29 Jul 2011 |
V209 |
Passing Loop 3 |
Mid loop signals modified |
| 29 Jul 2011 |
V210 |
Passing Loop 4 |
Mid loop signals modified |
| 5 Jul 2011 |
V141 |
Elders |
New Loop commissioned |
| 16 Jun 2011 |
V139 |
Batesford |
Evans Rd RLX now with boom gates |
| 26 May 2011 |
V208 |
Donnybrook |
Development of Passing Lane 2 |
| 6 May 2011 |
V143 |
Laverton |
Kororoit Rd now Overpass |
| 15 Mar 2011 |
V208 |
Donnybrook |
Engineers siding booked OOS |
| 3 Mar 2011 |
V214 |
Wangaratta |
New speed signs towards Sisley Ave RLX |
| 15 Feb 2011 |
V213 |
Benalla - Wodonga |
RLX distances amended |
| 15 Feb 2011 |
V214 |
Benalla - Wodonga |
RLX distances amended |
| 15 Feb 2011 |
V215 |
Benalla - Wodonga |
RLX distances amended |
| 15 Feb 2011 |
V216 |
Benalla - Wodonga |
RLX distances amended |
| 8 Feb 2011 |
V213 |
Benalla - Wodonga |
Corridor commissioned |
| 8 Feb 2011 |
V214 |
Benalla - Wodonga |
Corridor commissioned |
| 8 Feb 2011 |
V215 |
Benalla - Wodonga |
Corridor commissioned |
| 8 Feb 2011 |
V216 |
Benalla - Wodonga |
Corridor commissioned |
| 3 Feb 2011 |
V211 |
Seymour Loco |
Extra run around loop |
| 2 Feb 2010 |
V214 |
Alamatta |
Loop booked o.o.s |
| 2 Feb 2010 |
V213 |
Glenrowan |
Loop booked o.o.s |
| 10 Dec 2010 |
V213 |
Benalla |
Layout corrections at Up end |
| 10 Dec 2010 |
V212 |
Violet Town Siding |
layout changed (+ other notice boards added) |
| 10 Dec 2010 |
V129 |
Murtoa |
Signal changes |
| 10 Dec 2010 |
V125 |
Dimbolla |
Signal changes |
| 14 Nov 2010 |
V211 |
Seymour-Benalla |
Dual bi-directional lines commissioning |
| 14 Nov 2010 |
V213 |
Seymour-Benalla |
Dual bi-directional lines commissioning |
| 14 Nov 2010 |
V212 |
Seymour-Benalla |
Dual bi-directional lines commissioning |
13 Nov 2010 |
V213 |
Seymour-Benalla |
Dual bi-directional lines commissioning |
13 Nov 2010 |
V212 |
Seymour-Benalla |
Dual bi-directional lines commissioning |
| 30 Oct 2010 |
V212 |
Violet Town |
Loop booked o.o.s |
| 29 Oct 2010 |
V149 |
Appleton Dock |
Final details - North Dock Line commissioning |
| 27 Oct 2010 |
V148 |
South Dynon |
Added signal 142 |
| 1 Oct 2010 |
V149 |
Appleton Dock |
North Dock Line commissioning |
| 27 Sep 2010 |
V213-215 |
NE Line |
Signal installations |
| 27 Sep 2010 |
V141 |
Elders BP |
Removal of Elders Grade Xing |
| 23 Sep 2010 |
V211-216 |
NE West Line |
Changes involved in commissioning West Line with T/O working |
| 18 Aug 2010 |
V122 |
Kaniva |
Track changes |
| 14 Aug 2010 |
V139 |
Geringhap |
Engineers Siding closed |
| 21 Jul 2010 |
V144 |
Newport |
Hand off' slot details added |
| 21 Jul 2010 |
V145 |
Brooklyn |
Hand off' slot details added |
| 21 Jul 2010 |
V146 |
Tottenham |
Hand off' slot details added |
| 21 Jul 2010 |
V216 |
Wodonga |
Wodonga Bypass commissioned |
| 2 Jul 2010 |
V213 |
Benalla |
RLX 996 now has boom gates |
| 26 Jun 2010 |
V149 |
Moonee Ponds Junction |
Southern Cross (sg) is now V/Line |
| 21 Jun 2010 |
V126 |
Dahlen |
Up end siding TO removed |
| 21 Jun 2010 |
V131 |
Stawell |
Up end siding TO removed |
| 17 Jun 2010 |
V126 |
Pimpinio Siding |
Siding removed |
| 6 Jun 2010 |
V122 |
Miram |
Siding removed |
| 6 Jun 2010 |
V123 |
Tarraginnie |
Siding removed |
| 6 Jun 2010 |
V135 |
Tatyoon |
Melbourne bound DICS codes removed |
| 5 Jun 2010 |
V216 |
Wodonga |
Construction changes |
| 5 Jun 2010 |
V211 |
Seymour |
Seymour Loop Commissioned |
| 5 Jun 2010 |
V210 |
Seymour |
Added Signal SEY102 |
| 2 Jun 2010 |
V136 |
Vite Vite |
Added RLX numbers |
| 23 May 2010 |
V205 |
near Tottenham |
minor changes |
| 23 May 2010 |
V208 |
Plaasing Lane 2 |
Corrected signals |
| 23 May 2010 |
V211 |
Seymour |
Signalling |
| 23 May 2010 |
V212 |
Dual track |
Development of construction |
| 23 May 2010 |
V213 |
Benalla |
Connection to Oaklands line |
| 23 May 2010 |
V214 |
Dual track |
Development of construction |
| 23 May 2010 |
V215 |
Dual track |
Development of construction |
| 23 May 2010 |
V216 |
Dual track |
Development of construction |
| 23 May 2010 |
V121-V150 |
Western Line |
Series renumbered. Were
111-140 |
| 13 Mar 2010 |
V132 |
Laverton |
Adjacent b.g. Track changes |
| 13 Mar 2010 |
V209 |
Kilmore East Passing Lane |
Reconfigured PL Signals |
| 13 Mar 2010 |
V210 |
Tullarook Passing Lane |
Reconfigured PL Signals |
| 11 Mar 2010 |
V209 |
Broadford |
Reference to Old Broaford Loop removed |
| 6 Mar 2010 |
V127 |
Berrybank |
Speed to LX now 5 |
| 6 Mar 2010 |
V215 |
Wodonga West |
New developments |
| 6 Mar 2010 |
V216 |
Wodonga West |
New developments |
| 28 Jan 2010 |
V112 |
Kaniva Loop |
Corrected loop name |
| 21 Jan 2010 |
V205 |
McIntyre Loop |
Incorported Sunshine ex Drawing V204 |
| 21 Jan 2010 |
V135 |
Brooklyn |
Revised linking |
| 21 Jan 2010 |
V136 |
Tottenham |
Reconfigured as part of East West Divn. Was drawing V204 |
| 21 Jan 2010 |
V137 |
West Footscray |
Reconfigured as part of East West Divn. Was drawing V203 |
| 21 Jan 2010 |
V138 |
South Dynon - Sims St Jn |
Reconfigured as part of East West Divn. Was drawing V202 |
| 21 Jan 2010 |
V139 |
Docks Access |
Reconfigured as part of East West Divn. Was drawing V201 |
| 21 Jan 2010 |
V140 |
Melbourne Docks |
Reconfigured as part of East West Divn. Was drawing V200 |
| 24 Dec 2009 |
V201 |
Docks Access |
Re-development |
| 24 Dec 2009 |
V202 |
South Dynon |
Re-development |
| 28 Nov 2009 |
V202 |
Dynon |
Mods to sigs 136,138 &150 |
| 22 Sep 2009 |
V212 |
Euroa |
Amended RLX ID Nos. |
| 20 Sep 2009 |
V209 |
Heathcote Junction |
Corrected PedX ID |
| 18 Sep 2009 |
V216 |
Wodonga |
New Drawing - was V214 |
| 18 Sep 2009 |
V215 |
Chiltern |
New Drawing - was V213 |
| 18 Sep 2009 |
V214 |
Wangaratta |
New Drawing - was V213 |
| 18 Sep 2009 |
V213 |
Benalla - Glenrowan |
New Drawing - was V211/212 |
| 18 Sep 2009 |
V212 |
Avenel - Violet Town |
New Drawing - was V210 |
| 18 Sep 2009 |
V211 |
Seymour |
New Drawing - was V209 |
| 18 Sep 2009 |
V210 |
Tallarook Passing Lane |
New Drawing - was V208 |
| 18 Sep 2009 |
V209 |
Kilmore East Passing Lane |
New Drawing - was V207 |
| 18 Sep 2009 |
V208 |
Donnybrook - Wallan |
New Drawing - was V207 |
| 18 Sep 2009 |
V207 |
Craigieburn |
Detail additions |
| 18 Sep 2009 |
V206 |
Jacana |
Major changes - was V205 |
| 18 Sep 2009 |
V205 |
McIntyre Loop |
Sig ABJ6 sign added |
| 19 Sep 2009 |
V201 |
Melbourne Docks Access |
Junction track changes |
| 11 Aug 2009 |
V127 |
Werneth BP |
Added AAWS -Hamilton Hwy
RLX1516 |
| 11 Aug 2009 |
V118 |
Dooen |
Added AAWS -Henty Hwy
RLX1858 |
| 11 Aug 2009 |
V112 |
Kaniva |
Booms added - Madden St RLX 1926 & Farmers Rd RLX1925 |
| 10 Aug 2009 |
V205 |
McIntyre Loop |
New Drawing |
| 10 Aug 2009 |
V206 |
Jacana |
New Drawing |
| 10 Aug 2009 |
V207 |
Somerton |
New Drawing |
| 30 Jul 2009 |
V201 |
Melboune Docks Access |
Junction change. Added signals APD 26, 32, 34 38 & 42 |
| 26 Jul 2009 |
V200 |
Melbourne Docks |
New Drawing |
| |
|
|
|
| |
|
|
|
| |
|
|
|
| |
|
|
|
|
|
|
|